Domesstic wastewater system treatment for Nitigura Factory
Posted 29/11/2023- Domesstic wastewater system treatment for Nitigura Factory uses: MBBR according to Japanese Johkasou standards.
- The project is located at Hung Yen Province.
- Design, process the body and install.
- Completed in 11/2023.
NITIGURA FACTORY's domestic wastewater treatment system
Imported directly CE-18 model from Fujiclean - Japan
Address: Hung Yen Province
Contract package: Design, process the body and install.
Completion time: 11/2023
Output water quality: Pho Noi IP, Hung Yen.
Processing technology: MBBR according to Japanese Johkasou standards.












See more:
What technology does the project use?
Domesstic wastewater system treatment for Nitigura Factory uses: MBBR according to Japanese Johkasou standards.
Where was the project carried out?
The project is located at Hung Yen Province.
What did FUDESO deliver?
Design, process the body and install.
When was the project completed?
Completed in 11/2023.