Domestic wastewater treatment system in TDS Viet Nam plant

Domestic wastewater treatment system in TDS Viet Nam plant

Posted 20/11/2016
Quick summary
  • Domestic wastewater treatment system in TDS Viet Nam plant has a capacity of 34 m³.
  • Domestic wastewater treatment system in TDS Viet Nam plant uses: Jokaso Fudeso MBBR in accordance with Japanese Jokaso standard.
  • The project is located at Dong Van Industrial Zone , Duy Tien District, Ha Nam Province.
  • Design, construction and installation.
  • Completed in May 2014.

Domestic wastewater treatment system in tds Viet Nam plant, capacity:34M3

Investor: TDS Viet Nam Co., Ltd.
Address: Dong Van Industrial Zone , Duy Tien District, Ha Nam Province
Contract Package: Design, construction and installation
Performance time: February 2014
Completion Time: May 2014
Quality of output water: QCVN - 14/2008 collumn B
Treatment Technology: Jokaso Fudeso MBBR in accordance with Japanese Jokaso standard.

Hệ thống xử lý nước thải nhà máy TDS

Hệ thống xử lý nước thải nhà máy TDS Việt Nam Hệ thống xử lý nước thải nhà máy TDS Việt Nam


Figure 1: Domestic Wastewater treatment system in TDS Plant



Hệ thống xử lý nước thải nhà máy TDS Việt Nam Hệ thống xử lý nước thải nhà máy TDS Việt Nam

Figure 2: septic tank before operation for treatment system
Hệ thống xử lý nước thải nhà máy TDS Việt Nam

Figure 3: Control building of sewage treatement system
Trạm xử lý nước thải nhà máy TDS

Figure 4: MBBR (Moving Bed Biofilm Reactor) anaerobic microorganism tank
Slurry and sewage metering box

What is the treatment capacity of this project?

Domestic wastewater treatment system in TDS Viet Nam plant has a capacity of 34 m³.

What technology does the project use?

Domestic wastewater treatment system in TDS Viet Nam plant uses: Jokaso Fudeso MBBR in accordance with Japanese Jokaso standard.

Where was the project carried out?

The project is located at Dong Van Industrial Zone , Duy Tien District, Ha Nam Province.

What did FUDESO deliver?

Design, construction and installation.

When was the project completed?

Completed in May 2014.