Circular 75/2026/TT-BXD: drainage service pricing and the K coefficient by COD
Posted 26/11/2026Circular 75/2026/TT-BXD was signed on 30/09/2026 and takes effect from the date of signing (published in Official Gazette No. 555 dated 17/10/2026). It amends Circular 13/2018/TT-BXD on the method for pricing drainage services. The two most important changes are the price formula and the K coefficient based on the COD content of the wastewater.
Note: this content is for reference and is compiled from the original documents. When applying it to a specific project, check the original text and its validity status at the time of implementation.
Drainage service price formula
GDVTN = ZTB + (ZTB × P)
- ZTB: the average cost of drainage service per 1 m³ of wastewater.
- P: the norm profit rate on cost. For systems invested with state budget funds, P must not exceed 5%. For systems invested with other lawful sources of capital (including mixed capital), P is determined under Article 11 of Circular 45/2024/TT-BTC.
K coefficient for non-household drainage users
The service price that drainage users (other than household wastewater) pay to the drainage unit, calculated with the formula above, is multiplied by the K coefficient. K depends on the average COD in non-domestic wastewater, determined under clause 1 of Article 40 of Decree 80/2014/NĐ-CP.
| COD (mg/l) | K coefficient |
|---|---|
| ≤ 150 | 1 |
| 151 – 200 | 1.5 |
| 201 – 300 | 2 |
| 301 – 400 | 2.5 |
| 401 – 600 | 3.5 |
| > 600 | 4.5 |
Illustrative example (assumed numbers, not actual prices): if ZTB = 8,000 dong/m³ and P = 5%, the base price = 8,400 dong/m³. A facility with a COD of 250 mg/l (K = 2) pays 16,800 dong/m³; if it pretreats its wastewater so that COD falls to 150 mg/l (K = 1), it pays 8,400 dong/m³.
Cost structure of providing the service
The Circular replaces clause 1 of Article 4: total actual, reasonable and valid costs include direct material costs, direct labor, direct machinery and equipment, general production costs, other reasonable costs (if any) and enterprise management costs. The price of materials is the price delivered to the drainage and wastewater treatment site, determined under point b, clause 1, Article 9 of Circular 45/2024/TT-BTC.
What does this mean for production and service facilities?
- Facilities that discharge non-domestic wastewater into the urban drainage system pay fees based on COD: the higher the COD, the higher the K coefficient.
- Pretreatment at the source (grease separation, equalization, biological treatment) helps lower COD, which makes it easier to meet connection conditions and also reduces the K coefficient.
- The specific price is set by the provincial People's Committee (for example, Hải Phòng issued Decision 71/2026/QĐ-UBND, effective 01/01/2027), so you need to check the local document.
See also the compilation of the latest water supply and drainage standards and regulations.
Need advice for your project?
FUDESO engineers advise on wastewater, exhaust gas and environmental infrastructure solutions that comply with current regulations. Send your project details through the contact form or call the hotline (+84) 24 3206 3222.
Sources
- Circular 75/2026/TT-BXD (full text)
- Consolidated document 126/VBHN-BXD