New ventilation and air conditioning standards: TCVN 5687:2024 and QCVN 04-3:2026/BXD
Posted 26/11/2026For ventilation and air conditioning (HVAC) systems, the two major recent changes are TCVN 5687:2024, which replaces the 2010 design standard, and QCVN 04-3:2026/BXD, which replaces the energy efficiency regulation QCVN 09:2017/BXD and takes effect on 01/02/2027. This article compiles the documents up to 26/11/2026.
Note: this content is for reference and is compiled from the original documents. When applying it to a specific project, check the original text and its validity status at the time of implementation.
1. QCVN 04-3:2026/BXD: energy-efficient buildings
The regulation was issued with Circular 61/2026/TT-BXD dated 30/07/2026, takes effect on 01/02/2027 and replaces QCVN 09:2017/BXD. Before that date, QCVN 09:2017/BXD remains the current basis. The regulation includes parts on the building envelope, ventilation and air conditioning, lighting, other electrical equipment and energy performance control.
Some requirements on ventilation and air conditioning (section 2.2):
- Natural ventilation: the area of ventilation openings and operable windows in walls or roofs must not be less than 5% of the usable floor area of the room adjoining the outside.
- Mechanical ventilation: fans with motors above 0.56 kW must have an automatic control device that allows them to be switched off when not needed (except fans in continuously operating HVAC systems).
- Air conditioning: air conditioners and water chillers must meet the minimum COP efficiency indicators in the tables of the regulation.
2. TCVN 5687:2024: design requirements for ventilation and air conditioning
The standard sets requirements for the design and installation of ventilation and air conditioning systems for rooms in newly built or renovated civil buildings. It may be applied to industrial buildings that require ventilation and air conditioning to ensure thermal comfort and hygiene, unless the design brief specifies otherwise.
It does not apply to rooms in production buildings with technological processes; shelters; facilities with radioactive, flammable or explosive substances; mines; specialized heating, cooling and dust treatment systems; or central heating systems using hot water or steam.
3. Standards on fabrication, installation and equipment
| Code | Standard title | Notes |
|---|---|---|
| TCVN 5687:2024 | Ventilation and air conditioning – Design requirements | Replaces TCVN 5687:2010; prepared by the National Institute of Architecture (Ministry of Construction) |
| TCVN 13580:2023 | Ventilation and air conditioning – Requirements for duct fabrication | Round, oval and rectangular ducts, flexible ducts, air channels; hangers and supports |
| TCVN 13581:2023 | Ventilation and air conditioning – Requirements for duct installation and system acceptance | Installation of air ducts, refrigerant pipes, water pipes and equipment; acceptance |
| TCVN 13256:2026 | VRF/VRV air conditioners – Energy efficiency | Replaces TCVN 13256:2021 |
| TCVN 13591:2023 | Multi air conditioners – Energy efficiency | |
| TCVN 7830:2021 | Non-ducted air conditioners – Energy efficiency | |
| TCVN 14598:2025 | Safety guidelines for the manufacture, installation, repair and maintenance of household air conditioners using R-32 refrigerant | For installers and maintenance technicians working with R-32 units |
4. Fire safety related to ventilation
Ventilation systems are also subject to fire safety regulations, such as QCVN 06:2022/BXD (Amendment 1:2023) on fire safety for buildings and structures and QCVN 10:2025/BCA on the provision and arrangement of fire prevention, firefighting, and rescue equipment. HVAC design dossiers need to be checked against these regulations.
Tips for design and construction
- Projects implemented near or after the 01/02/2027 milestone should check the transitional provisions of Circular 61/2026/TT-BXD and the COP and fan control requirements of QCVN 04-3:2026/BXD so that equipment can be selected from the design stage.
- State the code and year of issuance of standards in the design report and contract, and avoid citing outdated versions such as TCVN 5687:2010.
- Accept the system according to TCVN 13581:2023; fabricate ducts according to TCVN 13580:2023.
Industrial exhaust gas treatment systems have their own regulations; see QCVN 19:2024 and how to choose a treatment tower.
Need advice for your project?
FUDESO engineers advise on wastewater, exhaust gas and environmental infrastructure solutions that comply with current regulations. Send your project details through the contact form or call the hotline (+84) 24 3206 3222.
Sources
- QCVN 04-3:2026/BXD
- TCVN 5687:2024
- TCVN 13580:2023
- TCVN 13581:2023
- TCVN 13256:2026
- TCVN 14598:2025